/ Licence for Alterations: What Office Tenants Need Before a Fit-Out

Licence for alterations: what office tenants need before a fit-out

What a licence for alterations is, what the law says about landlord consent, what the landlord’s surveyor will ask for and how to keep it off your critical path.

Share
Summarise
Greg DooleyMarketing ManagerDesign and Build Content Specialist.

Greg Dooley - Marketing Manager

In Brief

  • A licence for alterations is the landlord’s formal consent to your fit-out, recorded in a document that usually attaches your drawings and specifications.
  • Where your lease says consent is needed for improvements, section 19(2) of the Landlord and Tenant Act 1927 means the landlord cannot unreasonably withhold it.
  • There is no statutory deadline for a decision on alterations, so build several weeks to a few months into your programme and submit a complete package.
  • Agree reinstatement terms now. What the licence says about removing your works will shape your dilapidations bill when the lease ends.

Almost every office fit-out in a leased building needs the landlord’s permission. That permission usually takes the form of a licence for alterations, sometimes called a licence to alter. It is one of the documents most likely to hold up a project, and one of the least understood by the people planning the move.

This guide explains what a licence for alterations is, what the law says about consent, what a landlord’s surveyor will ask for, and how to keep it off your project’s critical path. It covers leases in England and Wales and is general guidance, not legal advice.

What a licence for alterations is

A licence for alterations is the formal record of the landlord’s consent to works in your premises. It typically attaches the drawings and specifications that were approved, sets conditions for how the works are carried out, and says what happens to them at the end of the lease (Brodies).

It is different from a deed of variation. A licence gives permission for specific works without changing the lease. A deed of variation permanently changes the lease terms, for example to add space, and needs more care because some changes can be treated as a surrender and regrant of the lease.

What your lease says about alterations

Start with the alterations covenant in your lease. It will usually fall into one of three types.

An absolute covenant prohibits certain alterations outright, often structural works. The landlord can refuse without giving a reason. A qualified covenant allows alterations with the landlord’s consent. A fully qualified covenant adds that consent is not to be unreasonably withheld.

Most office leases allow internal non-structural works, such as demountable partitions, with consent, and some allow minor works without it. Read the clause alongside any rules on services, floor loading and the building’s insurance.

The law on consent

Where a lease requires consent for improvements, section 19(2) of the Landlord and Tenant Act 1927 implies that consent is not to be unreasonably withheld. The landlord can still ask for a reasonable sum to cover any damage to or loss in value of its property, plus its reasonable legal and other expenses. Where an improvement adds nothing to the letting value, it can ask for a reasonable undertaking to reinstate.

The Landlord and Tenant Act 1988, which requires a decision within a reasonable time and written reasons, applies to applications to assign or sublet. It does not apply to alterations. A 2024 High Court case, Messenex Property Investments v Lanark Square, confirmed that alterations fall under the 1927 Act instead (Forsters). In practice, unreasonable delay can still amount to unreasonably withholding consent, but there is no statutory deadline.

What the landlord’s surveyor will ask for

Landlords usually pass applications to a building surveyor. Expect requests for most of the following (RICS Built Environment Journal).

Drawings and specifications

Existing and proposed layouts, ceiling and lighting plans, and specifications for partitions, finishes and joinery. Some estates set minimum scales. The Portman Estate’s guidance, for example, asks for drawings at 1:100 or larger.

Mechanical and electrical information

Drawings and calculations for any changes to air conditioning, ventilation, power, lighting, sprinklers, fire alarms and data. Anything that connects to base-build systems gets close attention.

Statutory approvals and safety information

Evidence of Building Regulations approval or a building control plans check, plus planning or listed building consent where relevant. You will also be asked for risk assessments and method statements, how you will meet the CDM Regulations 2015, an asbestos refurbishment and demolition survey where needed, and confirmation from the building’s insurer where the lease requires it.

Programme and logistics

A works programme, working hours, deliveries, use of lifts and loading bays, and how noisy works will be managed for other occupiers.

At completion the landlord will usually want operation and maintenance manuals, as-built drawings and test certificates, and may inspect during the works.

International law firm – Walnut Credenza with Brass Lamps and Artwork

Need drawings and M&E information for your landlord?

Our design team prepares the drawings, specifications and method statements landlords' surveyors ask for, and answers their questions as the design develops.

Building control and fire safety

Fit-out works and changes to partitions in offices generally need Building Regulations approval. The City of London, for example, lists both as work needing approval (City of London). Because offices fall under the Regulatory Reform (Fire Safety) Order 2005, the building notice route is generally not available, so allow time for a full plans application.

Since 1 October 2023, the dutyholder and competence duties introduced by the Building Safety Act 2022 apply to all Building Regulations work, not only high-rise residential buildings. In practice that means the client, principal designer and principal contractor roles must be filled by people with the right competence, which a landlord’s surveyor may ask you to show.

If your office is in a listed building, internal works that affect its character need listed building consent as well. Carrying out works without it is a criminal offence.

How long it takes and what it costs

Timescales vary by landlord and by how complete your application is. Published guidance gives some idea of the range. The Portman Estate says approval letters are normally issued within four weeks of a validated application, while the Cadogan estate aims to conclude licences within 90 days of receiving full information. Larger and more complex works take longer, especially where services or structure are affected.

Under an existing lease the tenant usually pays the landlord’s professional fees, including its solicitor and surveyor. Your solicitor will normally be asked for an undertaking to cover those costs before work on the licence starts. Some estates publish a fixed administration charge on top.

The practical lesson is to treat the licence as a programme item, not paperwork. If your fit-out needs to start on a set date, work back from it and submit early. Our guide to how long an office fit-out takes shows where consents sit in a typical programme.

platinum-office-glazed-private-offices-elevation
Glazed partitions, Platinum Equity, Mayfair
platinum-office-glass-meeting-rooms-black-framing
Private offices behind glass, Platinum Equity

Reinstatement: agree it now, not later

Most licences say what happens to your works when the lease ends. Some require you to remove everything. Others give the landlord the option to require removal by serving notice. A few accept that certain works can stay.

This clause matters more than it looks. It decides a large part of your dilapidations liability years from now. If you are installing quality meeting rooms, a kitchen or a reception that the next occupier would value, it is worth negotiating for them to stay. Take dated photographs of the premises before works start and keep a full set of the approved drawings with the licence.

How to get your licence approved faster

Submit a complete package the first time. Most delays come from rounds of questions about missing M&E information or method statements.

Talk to the landlord’s surveyor before you submit. A short meeting to walk through the design can surface concerns about services, noise or structure while they are still easy to change.

Keep the design within the building’s limits. Working with the existing grid, risers and ceiling zones makes approval simpler and usually saves money too.

Run the licence alongside your lease negotiations. If you are taking new space, design and the licence application can progress while the legals complete.

PJT Office Fit Out London - LARGE-25

How K2 can help

As a design and build contractor, K2 prepares the drawings, specifications, M&E information, method statements and programme that landlords’ surveyors ask for, and deals with their questions as the design develops. Because one team designs and builds, the information submitted is the information that gets built, which keeps the licence and the project in step. Read about our office fit-out service, see recent projects, or request a callback to talk through your programme.

Frequently asked questions

Do I need a licence for alterations for a Cat B fit-out?

Almost always. Most leases require the landlord’s consent for internal works such as partitions, ceilings and services, and the licence records that consent and its conditions.

Can a landlord refuse consent to alterations?

Under an absolute covenant, yes. Where consent is required for improvements, section 19(2) of the Landlord and Tenant Act 1927 means it cannot be unreasonably withheld.

How long does a licence for alterations take?

There is no statutory deadline. Published estate guidance ranges from about four weeks to 90 days after a complete application, and complex works take longer.

Who pays for the licence?

Usually the tenant, who covers the landlord’s reasonable legal and surveyor fees.

Spacious meeting areas for creative exchange

Plan your fit-out programme with us

Treat the licence as part of the programme. We plan consents, design and build together so your start date holds.