In Brief
- Dilapidations is the landlord’s claim for the cost of putting right breaches of your lease’s repair, decoration and reinstatement covenants when the lease ends.
- For leases in England and Wales, damages for disrepair are capped at the fall in value of the landlord’s interest under section 18(1) of the Landlord and Tenant Act 1927.
- The Dilapidations Protocol sets the timetable: the landlord’s schedule usually arrives within 56 days of the lease ending, and you usually have 56 days to respond.
- Get an assessment 12 to 18 months before your break or expiry date, while you can still choose between doing the works and negotiating a cash settlement.
Every office lease ends with a conversation about condition. If you have not planned for it, that conversation tends to arrive as a schedule of dilapidations and a demand for money, often weeks after you have moved out and spent your budget on the new office.
This guide explains how dilapidations work for office tenants in England and Wales, what limits a landlord’s claim, and how to plan the end of a lease so the bill is known, budgeted and, where possible, reduced. It is general guidance rather than legal advice. Your lease wording decides your obligations, so involve a building surveyor and a property solicitor early.
What dilapidations means
The RICS describes dilapidations as breaches of lease covenants that relate to the condition of a property, during or at the end of a tenancy (RICS consumer guide). In practice, a claim usually covers three things.
Repair covers anything your repairing covenant requires that is not in the required condition: damaged ceiling tiles, worn carpets, faulty fittings and, depending on the lease, building services. Reinstatement covers the removal of your alterations, such as partitions, meeting rooms, kitchens and raised floor changes, where the lease or a licence for alterations says they must come out. Redecoration covers the decorating covenant, which often requires redecoration in the last year of the term.
The landlord can also claim related losses where it can prove them, such as loss of rent while works are carried out, service charge for that period and professional fees.